Research / Old TraffordSource: FY2026 Form 20-F and dated announcements · checked 17 November 2026
Old Trafford and the proposed new stadium
Manchester United owns Old Trafford freehold, spent £29.0 million on it over the three years to 30 June 2026 and, in the year to 30 June 2026, spent £63.5 million on freehold property tied to its ambition to build a proposed new stadium nearby. This page sets out what the filing says about the stadium, its financing and its risks, then the club, council and planning announcements so far, each with its source and date.
Editorially reviewed. A snapshot as at the dates shown, not a live record.
01 / The answer
What the club owns and spends
The 20-F calls Old Trafford the most significant of the Group's real properties. It lists Old Trafford Football Stadium, Manchester, as a football stadium, owned freehold, with an area of approximately 205,000 square metres, held by Manchester United Football Club Limited. It lists Carrington training ground (Trafford) as owned freehold, approximately 440,000 square metres.
Company reported unless tagged Calculated. Debt explained · Advisers and counterparties · Who runs the club
| Year | Old Trafford | Carrington (approx.) | Freehold property for the proposed new stadium |
|---|---|---|---|
| Year ended 30 June 2026 | £7.7 million | £14.7 million | £63.5 million |
| Year ended 30 June 2025 | £13.1 million | £42.7 million | nil |
| Year ended 30 June 2024 | £8.2 million | £4.8 million | nil |
The 20-F records capital expenditure at Old Trafford of £7.7 million, £13.1 million and £8.2 million for the years ended 30 June 2026, 2025 and 2024. It separately gives approximately £14.7 million, £42.7 million and £4.8 million at Carrington, and says the 2025 rise reflects the new men's first team facility, which opened in August 2025. The year ended 30 June 2026 also includes £63.5 million of capital expenditure on freehold property related to the ambition to build a proposed new stadium, with no comparative expenditure in 2025 or 2024. It says Old Trafford investment is in refurbishment and regeneration, including hospitality suites and office and catering facilities. Manchester United plc FY2026 Form 20-F · Item 5.B Liquidity and Capital Resources, Capital expenditures at Old Trafford.
Calculated £29.0 million is the sum of the three Old Trafford figures: 7.7 + 13.1 + 8.2 = 29.0 (£ million, each figure as reported, rounded to £0.1 million). Manchester United plc FY2026 Form 20-F · Item 5.B Liquidity and Capital Resources, Capital expenditures at Old Trafford.
02 / The stadium
Capacity, history and what it secures
Old Trafford has a capacity of 74,500 (including accessible platforms for 556 disabled supporters). The 20-F describes it as the largest football club stadium in the United Kingdom, with approximately 10,000 executive club seats, including over 120 luxury boxes and 14 suites. It says home Premier League attendance has averaged over 99% of capacity in each of the last 28 years.
Manchester United plc FY2026 Form 20-F · Item 4, Our Business: Matchday; Revenue Sectors: Matchday
The 20-F says Old Trafford opened on 19 February 1910 with a capacity of approximately 80,000, was heavily damaged by bombing on 11 March 1941 and re-opened on 24 August 1949. Capacity fell to approximately 44,000 by 1992 with the move to all-seater, then grew to over 74,000 in 2006. It currently seats 74,500.
Manchester United plc FY2026 Form 20-F · Item 4, Our Footballing History
The 20-F says several owned properties, including Old Trafford, are encumbered with land charges as security for all obligations under the revolving facilities, the secured term loan facility and the senior secured notes. Manchester International Freight Terminal and Carrington are not encumbered. Note 13(i) says property, plant and equipment with a net book amount of £204.9 million (2025: £211.1 million) is pledged as security. That figure covers all pledged property, plant and equipment, not Old Trafford alone, and the 20-F does not give Old Trafford's carrying value separately.
Manchester United plc FY2026 Form 20-F · Item 4, Real Property; Note 13(i), Property, plant and equipment: assets pledged as security. For the facilities themselves see debt explained.
Note 13 shows freehold property with a net book amount of £312.0 million at 30 June 2026 (cost £390.2 million, accumulated depreciation £78.1 million), up from £216.6 million at 30 June 2025. Freehold property additions in the year were £64.8 million and transfers into freehold property from assets under construction £35.4 million. The note does not split out Old Trafford.
Note 13(ii) says land and assets under construction are not depreciated. Freehold property is depreciated over 75 years on a straight-line basis, except freehold property acquired before 1 August 1999, which is depreciated on a reducing balance basis at 1.33% a year.
Manchester United plc FY2026 Form 20-F · Note 13 Property, plant and equipment; Note 13(ii) Depreciation methods and useful lives.
03 / Spending and financing
What the filing says about the proposed new stadium
The 20-F says that in the year ended 30 June 2026 the Group acquired land and buildings off John Gilbert Way, Manchester, for £64.0 million. It says the acquisitions are held as freehold property and were made in conjunction with the Group's intention to build a proposed new stadium and, until those plans are progressed further, continue to generate rental income. The table lists the land and buildings off John Gilbert Way as owned freehold, approximately 106,000 square metres, owned by Alderley Urban Investments II Limited.
Manchester United plc FY2026 Form 20-F · Item 4, Real Property (final paragraph and key properties table). The filing says the Group acquired the land "for" this amount and does not say whether it includes costs. The filing does not name the seller. The club's announcement of 22 June 2026 (below) says it bought 25 acres from Indurent. We have not found a document that links the two, so we do not say they are the same purchase.
The 20-F gives three related figures for the year ended 30 June 2026 and does not reconcile them. Item 4 says the Group acquired land and buildings off John Gilbert Way for £64.0 million. Item 5.B says there was capital expenditure of £63.5 million for freehold property related to the ambition to build a proposed new stadium. Note 13 shows total additions to freehold property of £64.8 million (64,799 thousand), which covers all freehold additions, not only that land.
Manchester United plc FY2026 Form 20-F · Item 4 Real Property; Item 5.B Capital expenditures at Old Trafford; Note 13 Property, plant and equipment (additions)
Calculated Total freehold property additions in Note 13 (£64,799 thousand) are £1.3 million above the £63.5 million in Item 5.B and £0.8 million above the £64.0 million in Item 4, and the £64.0 million and £63.5 million figures differ by £0.5 million. The 20-F does not say what makes up any of these differences, whether the £64.0 million includes costs such as stamp duty, or what else is in the freehold additions.
64.799 - 63.5 = 1.3; 64.799 - 64.0 = 0.8; 64.0 - 63.5 = 0.5 (GBP million, reported figures, rounded to 0.1). Manchester United plc FY2026 Form 20-F · Item 4 Real Property; Item 5.B Capital expenditures at Old Trafford; Note 13 Property, plant and equipment (additions)
The club's fourth quarter and full year results release of 23 September 2026 says net capital expenditure on property, plant and equipment for the year was £85.9 million and that this includes £63.5 million of spend on the acquisition of land required as part of its ambition to build a new 100,000 seater stadium. It lists securing that land among its highlights. The passages that mention the stadium give no price for the land, no cost for the stadium and no funding plan.
Manchester United plc, Fourth quarter and full year fiscal 2026 results release (Exhibit 99.1 to Form 6-K), 23 September 2026 · Exhibit 99.1, Key Points; chief executive commentary; Cash flows paragraph. Read the release
Calculated In the year ended 30 June 2026 the three figures in Item 5.B (Old Trafford £7.7 million, Carrington approximately £14.7 million and freehold property for the proposed new stadium £63.5 million) add up to £85.9 million, the same as the £85.9 million of payments for property, plant and equipment in the cash flow statement (£85,919 thousand). The same sums do not match the cash flow payments in 2025 (£55.8 million against £44.7 million) or 2024 (£13.0 million against £17.5 million), and the 20-F does not say that the Item 5.B figures are cash measures.
7.7 + 14.7 + 63.5 = 85.9, against payments for property, plant and equipment of 85.919 in the cash flow statement. 2025: 13.1 + 42.7 = 55.8 against 44.721. 2024: 8.2 + 4.8 = 13.0 against 17.511. Manchester United plc FY2026 Form 20-F · Item 5.B Capital expenditures at Old Trafford; consolidated statement of cash flows (payments for property, plant and equipment)
Our reading The results release describes £63.5 million as spend on acquiring the land, within net capital expenditure of £85.9 million, which is consistent with the Item 5.B figure being a cash figure for 2026. The £64.0 million is the amount the filing says the land was acquired for. The filing and the release do not bridge the £0.5 million between those two figures or explain the rest of the freehold additions, so we show the figures as reported and do not choose between them.
The 20-F lists capital expenditure for the improvement of facilities at Old Trafford and Carrington among the Group's primary cash requirements. It says the Group maintains a mixture of long-term debt and capacity under its revolving facility so that funds are available for working capital, the playing squad and other capital projects, including those related to its ambition to build a proposed new stadium.
Manchester United plc FY2026 Form 20-F · Item 5.B Liquidity and Capital Resources (opening paragraph and the paragraph after the adidas minimum guarantee)
At 30 June 2026 the Group had contracted capital expenditure on property, plant and equipment of £454,000 (2025: £13,262,000), not recognised as liabilities. The 20-F does not say which projects these relate to.
Manchester United plc FY2026 Form 20-F · Item 5.B Liquidity and Capital Resources, Commitments; Note 32.1 Capital commitments
In the filing text the words "new stadium" appear four times: in the forward-looking statements notice, in Item 4 (Real Property) and twice in Item 5.B. In those passages we found no estimate of what a new stadium would cost, no funding plan, no timetable and no planning status, and we found no risk factor written about it. A fifth passage, in Item 5.B (net cash outflow from investing activities), uses the wording 'proposed new 100,000 seater stadium' and says the outflow was partly offset by expenditure on acquiring land for it; it gives no cost, funding plan, timetable or planning status either. This is our reading of what the filing contains, not a statement that no such plan exists.
Manchester United plc FY2026 Form 20-F · Item 3.D Risk Factors; Item 4; Item 5.B (search of the filing text for "new stadium" and "proposed new stadium")
04 / Risks the filing names
Risk factors that mention the stadium
The 20-F says revenue from ticket sales and other Matchday revenue at Old Trafford is highly dependent on continued attendance by individual and corporate supporters and on the number of home matches. It gives 20, 30 and 25 home matches in 2025/26, 2024/25 and 2023/24 and Matchday revenue of £153.5 million, £160.3 million and £137.1 million for the years ended 30 June 2026, 2025 and 2024.
Manchester United plc FY2026 Form 20-F · Item 3.D Risk Factors: Matchday revenue from our supporters is a significant portion of overall revenue
The 20-F says: "Our most valuable tangible asset is the Old Trafford stadium." It says an inability to renew insurance policies covering players, Old Trafford, Carrington or other valuable assets could expose the Group to significant losses, and that some activities or assets may be uninsured if policies cannot be renewed on the same terms.
Manchester United plc FY2026 Form 20-F · Item 3.D Risk Factors: insurance
The 20-F says any prolonged business interruption at Old Trafford could cause a decline in Matchday revenue, and that business interruption insurance covers some but not all of these events and may not fully compensate the Group for loss. A separate risk factor says extreme weather may cause property damage or interrupt Matchday operations at Old Trafford.
Manchester United plc FY2026 Form 20-F · Item 3.D Risk Factors: Business interruptions due to natural disasters, terrorist incidents and other events
The 20-F lists the Sports Ground Safety Authority (SGSA) rules, ISO 45001:2018 certification and fire safety measures among the obligations the Group must meet. It says a health and safety incident at the stadium could lead to claims, fines, reputational damage, closure or capacity reductions of facilities and prosecution.
Manchester United plc FY2026 Form 20-F · Item 3.D Risk Factors: Non-compliance with health and safety legislation could lead to physical harm
05 / Plans and announcements
The proposal, in date order
These come from the club (its news items, its results release and the minutes of its Fans' Forum), Trafford Council and its Executive. They record what each said on the date shown. The Fans' Forum minutes are the club's own summary of a meeting, not a transcript. The figures for jobs, homes and economic benefit are the club's estimates of potential benefits, not outcomes.
The club reported that the Old Trafford Regeneration Task Force had submitted an Options Report to executive bodies at Manchester United, the Greater Manchester Combined Authority and Trafford Borough Council. The Task Force determined that a redeveloped Old Trafford could increase capacity to 87,000 and a new-build stadium to 100,000. More than 50,000 fans were surveyed: 52% preferred a new-build stadium, 31% redevelopment and 17% were unsure.
Club News, 17 January 2025 (Options Report findings). Read the original
The club reported a UK Treasury statement that the Chancellor was championing the Old Trafford project. In the same piece the club said it "would be responsible for the stadium development" and that support from public bodies would be needed to unlock the wider regeneration opportunity, including improved transport infrastructure and housing.
Club News, 26 January 2025. Read the original
On 11 March 2025 the club announced its intention to pursue a new 100,000-seater stadium as the centrepiece of the regeneration of the Old Trafford area. It said Foster + Partners, appointed to design the stadium district, had unveiled conceptual images, which would provide a masterplan for further feasibility, consultation, design and planning work. It said it had concluded a new stadium was the right way forward and would carry out further consultation before final decisions.
Club News, 11 March 2025. Read the original
In March 2025 the club said the stadium and wider regeneration had the potential to add £7.3 billion a year to the UK economy, including the possible creation of 92,000 new jobs and more than 17,000 new homes. These are the club's estimates of potential benefits, not outcomes.
Club News, 11 March 2025 (economic benefit estimates). Read the original
The club reported the official launch of the Old Trafford Regeneration Mayoral Development Corporation (OTR MDC), chaired by Lord Coe, as the body driving transformation of the 370-acre Old Trafford area. The club said the MDC would support delivery of more than 15,000 new homes and 90,000 jobs, and supports the ambition for a new 100,000-capacity stadium.
Club News, 23 January 2026. Read the original
In a club article of 24 March 2026 summarising an episode of its Inside Carrington podcast, a club executive says the club has had a lot of interest from people and organisations that want to invest in the stadium and the wider stadium district, and that those conversations are naturally behind closed doors. The executive says a build of this complexity takes one or two years to get ready for construction, which includes getting the land assembled, the funds in place and planning permission, that this is the stage the club is at, and that no opening date has been named. The article gives no amounts.
Club news item, investment and timeline passages. Read the original
On 22 June 2026 the club said it had secured the majority of the land required for a new 100,000-seater stadium: 25 acres, about 350 metres north-west of the current stadium, acquired from Indurent, described as a Blackstone portfolio company. The club said it would engage directly with businesses affected. The announcement does not state a price.
Club News, 22 June 2026. Read the original
On 23 June 2026 Trafford Council said it supported Manchester United securing the majority of the land required for its new 100,000-seater stadium. It said the club had worked with the Council and the Old Trafford Regeneration Mayoral Development Corporation, and that a Strategic Masterplan for Trafford Wharfside, prepared by the Council with support from the MDC and the Greater Manchester Combined Authority, would be published on 9 July.
Council news release, 23 June 2026. Read the original
In July 2026 the club described the masterplan vision as 48,000 local jobs and 15,000 new homes across 150 hectares, with potential to add £7.3 billion a year to the UK economy. These are the club's description of the vision, not outcomes.
Club News, 9 July 2026 (masterplan vision). Read the original
On 9 July 2026 the club confirmed the proposed location of its new 100,000-seater stadium: the heart of a new Stadium District, approximately 350 metres north-west of the existing stadium, as part of the Trafford Wharfside masterplan published by Trafford Council. The article notes: "No decision has been made regarding the future of the existing Old Trafford stadium."
Club News, 9 July 2026. Read the original
At the same meeting the Executive approved the Trafford Local Plan (Publication Version) 2026 for a six-week representations period beginning no earlier than 3 August 2026. The decision text says the plan includes "reference to the potential use of compulsory purchase powers to assist with site assembly". The decision text we read does not name the stadium.
Executive 20 July 2026, item 5 Local Plan Regulation 19 Consultation Approval (printed decision). Read the original
The Executive resolved to approve the draft Trafford Wharfside Strategic Masterplan for consultation and to note that on adoption it would be a development document forming part of the planning policy framework for the Wharfside area, superseding the previous Wharfside Development Framework and Wharfside Masterplan.
Executive 20 July 2026, item 4 Wharfside Strategic Masterplan (printed decision). Read the original
Trafford Council's web page says it approved the draft Wharfside Strategic Masterplan on 20 July 2026 and ran a formal eight-week consultation from 28 July to 22 September 2026. It says a final version will go to the Council's Executive for adoption in autumn 2026.
Trafford Council web page, Wharfside Strategic Masterplan (as read 14 November 2026). Read the original
The club's fourth quarter and full year results release of 23 September 2026 says net capital expenditure on property, plant and equipment for the year was £85.9 million and that this includes £63.5 million of spend on the acquisition of land required as part of its ambition to build a new 100,000 seater stadium. It lists securing that land among its highlights. The passages that mention the stadium give no price for the land, no cost for the stadium and no funding plan.
Exhibit 99.1, Key Points; chief executive commentary; Cash flows paragraph. Read the original
The club's minutes of the Fans' Forum meeting of 23 October 2026 record it saying that over the previous three months it had onboarded strategic consultants to proceed with the design stage of the new stadium, that the next six months are focused on RIBA Stages 1 and 2 (Stage 1 being fan requirements and priorities), and that a new stadium survey launched on the day of the meeting would close on 6 November 2026, to be followed by six in-person focus groups. In the question and answer notes the club is recorded as outlining timings for RIBA Stages 1, 2 and 3 to develop a design 'ready for planning submission', and as relaying its intention to be playing in the new stadium in advance of its stated aim of hosting the Women's World Cup in 2035.
Fans' Forum minutes, 23 October 2026, 'Stadium update' and question and answer notes (pages 3 to 5). Read the original
The same minutes record a representative asking the club to share more detail on the request-for-proposals process for onboarding consultants to develop the stadium commercial model, for example personal seat licences, because fans are concerned about funding of the new stadium. The club is recorded as saying this information is confidential. In answer to another representative's concern about the ethical nature of funding given the club's relationship with the council, the club is recorded as saying it is engaged with the council on the wider infrastructure and that it is for the club to build a robust business case for the stadium itself.
Fans' Forum minutes, 23 October 2026, 'Stadium update' question and answer notes (page 5). Read the original
The same minutes record the club saying it is actively engaged with landowners, Trafford Council and the Mayoral Development Corporation to ensure mutual agreements on land assembly required for the new stadium, and that it previously announced buying a 25-acre plot about 350 metres north-west of the current stadium from Indurent, which it describes as a leading provider of industrial space and a Blackstone portfolio company. They record that the public consultation led by Trafford Council on the wider masterplan had closed and that results would be published in due course.
Fans' Forum minutes, 23 October 2026, 'Stadium update' (page 3). Read the original
06 / What it means
Reading the record, and its limits
Our reading The filing treats the new stadium as an ambition and a proposal. It shows money already spent on land, and a funding approach that rests on the group's existing debt and revolving facility, but not a cost, a funding plan or a start date. The public announcements describe a larger programme, with public bodies leading the wider regeneration and the club responsible for the stadium itself, and they too carry no published cost in the pages we read.
Read together, the club's two sets of estimates differ: 92,000 jobs and more than 17,000 homes (March 2025) against 48,000 local jobs and 15,000 homes (July 2026). The articles use different areas and wording (national jobs against local jobs, a 370-acre area against 150 hectares), so we do not treat one as correcting the other. Both are projections.
Club News, 11 March 2025 and 9 July 2026
On 17 November 2026 a keyword search of Trafford Council's online planning register for 'new stadium' returned three applications, received in 1997, 2009 and 2011, and a search for 'Alderley Urban' (the owner the 20-F names for the John Gilbert Way land) returned no results. We found no planning application for the proposed new stadium. The club's October 2026 Fans' Forum minutes describe design work towards a planning submission. This is our reading of two keyword searches, not a statement that no application, scoping request or pre-application discussion exists.
Trafford Council online planning register (keyword searches run on 17 November 2026). Open the register
What this page does not cover
- The cost of a new stadium, how it would be paid for and who would lend or invest. We found no documented figure or plan from the club, the Council, the filing or the results release, so none is shown. The club's March 2026 article says investment conversations are behind closed doors, and its October 2026 Fans' Forum minutes record it calling the stadium commercial-model process confidential and saying it is for the club to build a business case.
- The price of the land from an independent record. The only price in a primary source is the 20-F's £64.0 million (and the related £63.5 million and £64.8 million figures above). We did not check HM Land Registry, which needs a title number and a paid search, so there is no independent record of the price here.
- A planning application or decision for the stadium. The sources we read describe a draft masterplan and a Local Plan consultation, not a planning decision, and our searches of Trafford's planning register found no stadium application. We have not searched by map or area or read the Planning Committee agendas, and the club's October 2026 minutes describe design work towards a planning submission.
- What happens to the existing stadium. The club's 9 July 2026 article says no decision has been made.
- Old Trafford's own carrying value, depreciation or maintenance backlog. The filing does not give them separately.
- Structural condition, safety inspections or any engineering opinion. Earlier unsourced exhibits on these were withdrawn: see the corrections register. We do not publish a stadium condition record.
- Press reports, fan commentary and estimates from outside the club and the Council, and anything said after the dates shown.
07 / Sources
Where this comes from
Manchester United plc (filed with the US Securities and Exchange Commission). Accession 0001104659-26-110384. Items 3.D, 4 and 5.B, Notes 13 and 32, and the cash flow statement.
- Old Trafford Task Force completes feasibility work, Manchester United, 17 January 2025. Checked 14 November 2026.
- Regeneration Project backed by government, Manchester United, 26 January 2025. Checked 14 November 2026.
- United confirms ambition to build a new stadium, Manchester United, 11 March 2025. Checked 14 November 2026.
- United welcome landmark moment in Old Trafford regeneration plan, Manchester United, 23 January 2026. Checked 14 November 2026.
- Roche's Old Trafford Regeneration update, Manchester United, 24 March 2026. Checked 17 November 2026.
- United secures land for new 100,000-seater stadium, Manchester United, 22 June 2026. Checked 14 November 2026.
- Trafford Council welcomes major milestone in MUFC stadium plans, Trafford Council, 23 June 2026. Checked 14 November 2026.
- Revealing the location of our new stadium, Manchester United, 9 July 2026. Checked 14 November 2026.
- Trafford Council Executive, 20 July 2026: agenda and decisions (items 4 Wharfside Strategic Masterplan and 5 Local Plan Regulation 19), Trafford Council, 20 July 2026. Checked 14 November 2026.
- Wharfside Strategic Masterplan, Trafford Council, 28 July 2026. Checked 14 November 2026.
- Manchester United plc, Fourth quarter and full year fiscal 2026 results release (Exhibit 99.1 to Form 6-K), Manchester United plc, 23 September 2026. Checked 17 November 2026.
- Fans' Forum minutes, meeting of 23 October 2026, Manchester United, 23 October 2026. Checked 17 November 2026.
- Trafford Council online planning register (keyword searches run on 17 November 2026), Trafford Council, 17 November 2026. Checked 17 November 2026.
Mistake or missing change? See the corrections register or contact us. How we verify: methodology.